RT Infrastructure Solutions (RTIS) is pleased to announce that it has been awarded a key contract by Amey to carry out vital treadle modification works.
This essential project aims to enhance road user safety by addressing the risks associated with wrong-direction train movements at Codford, Upton Lovell, and Wylye level crossings.
The project will involve identifying affected treadles and converting them to directional operation, ensuring that strike-in treadles activate only in the normal direction of travel, thereby preventing unintended activations by wrong-direction moves.
To maintain cost efficiency and align with best practices in the Western Region, Twin Arm Forfex Treadles will be installed to replace single-arm configurations.
RTIS is proud to support Amey in delivering these safety-critical enhancements, reinforcing its expertise in railway signalling solutions and its commitment to maintaining a reliable and secure rail network.
Activities Undertaken
-
Production of Master Test Plan and Test & Commissioning Plans
-
Provision of a Signalling Engineering Manager for all sites
-
Signalling Surveys for all sites
-
Signalling Prep Testing for all sites
-
Scheme/Bonding Plan Verification for all sites
-
Signalling Test & Commissioning for all sites
-
Production of SWTH Testing Documentation
-
Testing Support for First Train Movements
-
SMTH Support for all sites
client
Amey
Project value
£113,000
duration
Jan 2025 – March 2025